Loading...

Construction of Loop (Saidabad Side) of Khilgaon Flyover. (Khilgaon-Flyover)

Khilgaon-Flyover: The government undertook a number of remedial measures to address the public sufferings caused by intolerable traffic congestions in Dhaka city. As a part of the total initiatives to improve the traffic situation in Dhaka the then government approved the Khilgaon Flyover project in the ECNEC meeting on 09/02/2000. Accordingly LGED constructed the    more...
Project Information Table
Implementing Agency : LGED
Project Code : 59
Project Name : Construction of Loop (Saidabad Side) of Khilgaon Flyover.
Name of PD : A K Azad
Date of Approval :
Starting Date : Oct-2010
Completion Date : Dec-2015
Financial Year :
Source of Fund :
Total GOB PA
Project Cost : 7462.96 Lac
Commulative Expenditure :
Physical Progress :
Progress Reporting Date :
Comments :

At a Glance
Short Title: Khilgaon-Flyover
Ministry: LGRD
Executing Agency: LGED
Approval Ref:
Project Code: 59
Sector: Urban
Status: Ongoing Investment Project
Donor: GOB.
Budget: 7462.96 Lac
Start Date: Oct-2010
Completion Date: Dec-2015
Name of PD: A K Azad
Procurement